It is exciting to be on the leading edge of our fast-paced industry. The 426-unit job was paved to base asphalt less than 12-weeks after receiving the storm ECA’s, despite having challenging features including deep servicing, two SWM Ponds, and a sensitive wetland to protect. The project met an unprecedented schedule and delivered a fully permit-serviced site to our client, less than 12-months after the first submission drawings.

Ben,
Project Manager, Milton Team